Project Estimation Guide
Document Control​
- Last Updated: February 4, 2025
- Version: 2.0.0
- Status: Active
- Owner: Project Management Team
- Next Review: May 4, 2025
Overview​
At GravityVC, we follow a bottom-up approach for project estimation. This approach involves breaking down projects into small, manageable work items that can be completed within 4 hours or less. By aggregating these granular estimates, we create accurate and reliable project timelines.
Core Principles​
- Maximum Task Size: Each work item should be estimated at 4 hours maximum
- Granular Breakdown: Projects must be broken down into detailed, specific tasks
- Clear Deliverables: Each task should have a clear, measurable outcome
- Buffer Inclusion: Add 20% buffer for unforeseen complexities
- Regular Review: Review and adjust estimates based on actual progress
Estimation Process​
1. Project Breakdown​
- Break the project into major features
- Divide features into components
- Split components into specific tasks
- Ensure each task is ≤ 4 hours
2. Task Definition​
Each task should include:
- Clear description
- Definition of Done
- Dependencies
- Required skills
- Expected output
3. Effort Estimation​
- Estimate each task in hours (max 4)
- Consider complexity factors
- Account for dependencies
- Include review time
- Add testing effort
4. Buffer Calculation​
- Technical buffer: 10%
- Communication buffer: 5%
- Integration buffer: 5%
Example Project Estimation​
Project: E-commerce Product Catalog​
1. Feature Breakdown​
| Feature | Components | Tasks (≤4h each) | Hours |
|---|---|---|---|
| Product Listing | Frontend UI | Design product card component | 4 |
| Implement grid layout | 4 | ||
| Add sorting functionality | 4 | ||
| Implement filters UI | 4 | ||
| Backend API | Design database schema | 3 | |
| Create CRUD endpoints | 4 | ||
| Implement search API | 4 | ||
| Add filtering logic | 4 | ||
| Integration | Connect frontend with API | 3 | |
| Implement error handling | 2 | ||
| Add loading states | 2 | ||
| Product Details | Frontend UI | Design detail page layout | 4 |
| Implement image gallery | 4 | ||
| Add specifications section | 3 | ||
| Create related products component | 4 | ||
| Backend API | Create product detail endpoint | 3 | |
| Add related products logic | 4 | ||
| Implement caching | 4 | ||
| Integration | Connect with backend | 2 | |
| Add error states | 2 | ||
| Implement loading skeleton | 3 |
2. Effort Summary​
| Category | Raw Hours | With Buffer (20%) |
|---|---|---|
| Frontend Development | 32 | 38.4 |
| Backend Development | 22 | 26.4 |
| Integration | 14 | 16.8 |
| Total | 68 | 81.6 |
3. Timeline Calculation​
| Factor | Hours | Days (8h/day) |
|---|---|---|
| Raw Development Time | 68 | 8.5 |
| With 20% Buffer | 81.6 | 10.2 |
| Final Estimate | 82 | 11 |
Task Breakdown Template​
Feature: [Feature Name]
Description: [Brief description of the feature]
Components:
1. [Component Name]
- Task: [Specific task ≤4h]
* Description: [Clear description]
* Dependencies: [List dependencies]
* Skills Required: [Required skills]
* Expected Output: [Measurable outcome]
* Estimated Hours: [≤4]
Best Practices​
Do's​
- Break down tasks until they're ≤4 hours
- Include time for code review and testing
- Consider dependencies and integration points
- Account for documentation time
- Include buffer for unforeseen issues
Don'ts​
- Create tasks larger than 4 hours
- Ignore dependencies between tasks
- Skip buffer allocation
- Forget about non-coding activities
- Underestimate integration complexity
Estimation Review Checklist​
- All tasks are ≤4 hours
- Dependencies are identified
- Buffer is included
- Integration points are considered
- Non-development tasks are included
- Review and testing time allocated
- Documentation effort included
Related Documents​
- Project Planning Template
- Work Breakdown Structure Guide
- Risk Assessment Template
- Resource Allocation Guide