Project Estimation Guide

Document Control​

  • Last Updated: February 4, 2025
  • Version: 2.0.0
  • Status: Active
  • Owner: Project Management Team
  • Next Review: May 4, 2025

Overview​

At GravityVC, we follow a bottom-up approach for project estimation. This approach involves breaking down projects into small, manageable work items that can be completed within 4 hours or less. By aggregating these granular estimates, we create accurate and reliable project timelines.

Core Principles​

  1. Maximum Task Size: Each work item should be estimated at 4 hours maximum
  2. Granular Breakdown: Projects must be broken down into detailed, specific tasks
  3. Clear Deliverables: Each task should have a clear, measurable outcome
  4. Buffer Inclusion: Add 20% buffer for unforeseen complexities
  5. Regular Review: Review and adjust estimates based on actual progress

Estimation Process​

1. Project Breakdown​

  1. Break the project into major features
  2. Divide features into components
  3. Split components into specific tasks
  4. Ensure each task is ≤ 4 hours

2. Task Definition​

Each task should include:

  • Clear description
  • Definition of Done
  • Dependencies
  • Required skills
  • Expected output

3. Effort Estimation​

  • Estimate each task in hours (max 4)
  • Consider complexity factors
  • Account for dependencies
  • Include review time
  • Add testing effort

4. Buffer Calculation​

  • Technical buffer: 10%
  • Communication buffer: 5%
  • Integration buffer: 5%

Example Project Estimation​

Project: E-commerce Product Catalog​

1. Feature Breakdown​

FeatureComponentsTasks (≤4h each)Hours
Product ListingFrontend UIDesign product card component4
Implement grid layout4
Add sorting functionality4
Implement filters UI4
Backend APIDesign database schema3
Create CRUD endpoints4
Implement search API4
Add filtering logic4
IntegrationConnect frontend with API3
Implement error handling2
Add loading states2
Product DetailsFrontend UIDesign detail page layout4
Implement image gallery4
Add specifications section3
Create related products component4
Backend APICreate product detail endpoint3
Add related products logic4
Implement caching4
IntegrationConnect with backend2
Add error states2
Implement loading skeleton3

2. Effort Summary​

CategoryRaw HoursWith Buffer (20%)
Frontend Development3238.4
Backend Development2226.4
Integration1416.8
Total6881.6

3. Timeline Calculation​

FactorHoursDays (8h/day)
Raw Development Time688.5
With 20% Buffer81.610.2
Final Estimate8211

Task Breakdown Template​

Feature: [Feature Name]
Description: [Brief description of the feature]

Components:
1. [Component Name]
- Task: [Specific task ≤4h]
* Description: [Clear description]
* Dependencies: [List dependencies]
* Skills Required: [Required skills]
* Expected Output: [Measurable outcome]
* Estimated Hours: [≤4]

Best Practices​

Do's​

  • Break down tasks until they're ≤4 hours
  • Include time for code review and testing
  • Consider dependencies and integration points
  • Account for documentation time
  • Include buffer for unforeseen issues

Don'ts​

  • Create tasks larger than 4 hours
  • Ignore dependencies between tasks
  • Skip buffer allocation
  • Forget about non-coding activities
  • Underestimate integration complexity

Estimation Review Checklist​

  • All tasks are ≤4 hours
  • Dependencies are identified
  • Buffer is included
  • Integration points are considered
  • Non-development tasks are included
  • Review and testing time allocated
  • Documentation effort included